Published on December 01, 2023 - Carbovac

How does it go for a VRU deployment ❔

Once the contract is signed, products manufactured and delivered on-site, and assembly achieved, the VRU set up is made with 2 steps :
– Cold commissioning : test without any product, to check materials, electronics, pneumatics, leak detection towards air
– Hot commissioning : test in real conditions, with real products. This is followed by the fine-tuning step, the final adjustment to optimize parameters and functions.
Once everything is in order, the GO can be given for the launch and commissioning of the VRU. Standard Zephyr projects are designed for truck loading. The Zephyr 32 can load 1 truck, the Zephyr 64 2 trucks and the Zephyr 128 4 trucks.

#LUVEBA #CARBOVAC #ALMAGROUP #ZEPHYRVRU #VRU #URV#COMMISSIONNING #VOCRECYCLING #ENVIRONMENT

Published on December 01, 2023 - Carbovac

These articles might interest you

  • Alma
    https://www.alma-group.com/wp-content/uploads/2024/07/onexpo-mexique.jpg
    ONEXPO 2024 02 July 2024 News
    Our International Sales Manager Paul-Junior Tuta had the pleasure of taking part with our partner Petrogas Corporation in the Onexpo Nacional A. C. 2024, held from 18 to 20 June at the Cancun Center. Thank you to our partner Petrogas Corporation and to everyone who visited our stand and shared this...
    Read more
  • EMIR
    https://www.alma-group.com/wp-content/uploads/2023/04/Carte-Mayotte-1.png
    SUCCESS STORY EMIR ! 28 April 2023 News
    EMIR gains additional functionality on its contract with our main client Total Energies in Mayotte ! The scope of action is extended to line up to the usual contracts that we had for gas stations in Reunion island and the French Carribeans. Congrats to all the team for their constant work on this wi...
    Read more
  • Alma services
    https://www.alma-group.com/wp-content/uploads/2024/02/AS-Total-proxi-2_2.jpg
    A new installation ! 22 February 2024 News
    For our client Total Proxi Energies, our ALMA SERVICES teams were in charge of transforming a 3-arm Dôme loading source and calibrating them. This operation included prefabrication of the Source skid in our workshops, removal of the Dôme bridge, installation of the skid on site and electrical and...
    Read more
Certifications

Recognition of our security and regulatory commitments

Recruitment

Join a growing group